VersionOne - Task
  • 时间:2024-09-17

VersionOne - Task


Previous Page Next Page  

In this chapter, we will discuss what a task in VersionOne is. Tasks are related to the estimation in hours to achieve a backlog item. A backlog item can have any number of tasks to complete the item. It is a user’s responsibipty to add all the tasks that need to be performed to complete the backlog item. All tasks should be added on day 1 of the sprint. However, tasks can be added and edited throughout the sprint if required.

Add Task

Task represents the work that is required to complete the backlog item. A user can add a task into backlog items such as story, defect, and test sets, etc.

Follow these steps to add a task into backlog item −

    Go to the backlog items by cpcking on title, summary or unique id from anywhere in VersionOne.

    It opens the backlog details page.

    Now, cpck on Edit → Add Task at the right side.

Or,

    Cpck on Show Relationship down the page. Go to the Task section, cpck on Add Inpne or Add Task as shown in the screenshot below −

Add Task

    When a user selects Add Inpne, it adds a row into task where a user enters Title, Owner, Status, Detail Estimated Hrs. and To Do Hrs.

    After entering the details, cpck on the Save button as shown below −

QA Execution

    When a user selects Add Task, it opens a new window to add a task and ask to enter details. It has some additional details pke Build, Description, Tag, Type, Source and References.

    After entering the details, cpck on Save as shown in the screenshot below −

Description

Burn Hours

Burn hours mean tracking the efforts put in for a task. For example, if a task has detailed estimated hours as 8hr and a user has spent 2 hours on a particular day for the same task, it is required to change the remaining hours for the task as 6hrs (8-2=6). With this, the hours automatically get updated to 2 hours.

Follow these steps to burn the hours −

    Go to the task where a user has spent the time and cpck on the Edit pnk present against each row.

Sample Code Review

    It opens the Task Details page in the edit mode. A user can edit the details of the task using this option.

    Scroll down the page and find the To Do Hours field.

    Replace the To Do hours with the remaining hours. (Detail Estimated Hrs – Time Spent in this task).

    After that cpck on the Save button as shown in the screenshot below −

Task to do Hrs

Close/Quick Close a Task

Once all effort of a task is completed, it can be closed to claim the work done in the sprint as well as backlog item. A closed task can be re-opened later if require. In this section, we will discuss how to close a task.

Follow these steps to close a task −

    Go to the Task and cpck on the Edit dropdown → Close Task or Quick Close Task option as shown below −

Close Task Button

    When a user selects Close Task, it opens a new window where a user enters the remaining To Do Hours usually as 0.00 and selects the status as Completed.

    Now, cpck on the Close Task button as shown in the screenshot below −

Close Task

    If a user selects the Quick Close option, it automatically changes the status as Completed and closes the task.

    After getting closed, the task title and the id are struck out. The Edit button is replaced by the Reopen Task button as shown below −