- EVM - Examples
- EVM - Miscellaneous Formula
- EVM - Schedule Variance
- EVM - Cost Variance
- EVM - Basic Elements
- EVM - Overview
- EVM - Home
Earn Value Management Resources
Selected Reading
- Who is Who
- Computer Glossary
- HR Interview Questions
- Effective Resume Writing
- Questions and Answers
- UPSC IAS Exams Notes
EVM - Basic Elements
EVM consists of the following three basic elements:
Planned Value
Actual Cost
Earned Value
All the three elements are captured on a regular basis as of a reporting date.
Planned Value
Planned value (PV) is also referred to as Budgeted Cost of Work Scheduled (BCWS). PV or BCWS is the total cost of the work scheduled/planned as of a reporting date.
It is calculated as:
PV or BCWS = Hourly Rate × Total Hours Planned or Scheduled
NOTE: Hourly Rate is the rate at which effort will be valued.
Actual Cost
Actual cost (AC) is also referred to as Actual Cost of Work Performed (ACWP). AC or ACWP is the total cost taken to complete the work as of a reporting date.
It is calculated as:
AC or ACWP = Hourly Rate × Total Hours Spent
Earned Value
Earned value (EV) is also referred to as Budgeted Cost of Work Performed (BCWP). EV or BCWP is the total cost of the work completed/performed as of a reporting date.
It is calculated as:
EV or BCWP = Basepned Cost × % Complete Actual
All these three elements can be derived from Work Breakdown Structure by associating the costs to each of the tasks. For a big project, it will be a tedious task to calculate these elements manually. Schedupng software tools pke Microsoft Project is used to calculate these three elements.
NOTE: % Completed Planned and % Completed Actual are defined below.
% Completed Planned
The percentage of work which was planned to be completed by the Reporting Date. It is calculated using the following formula:
% Completed Planned = PV / BAC
% Completed Actual
The percentage of work which was actually completed by the Reporting Date. It is calculated using the following formula:
% Completed Actual = AC / EACAdvertisements