English 中文(简体)
JIRA - Burndown Chart
  • 时间:2024-11-05

JIRA - Burndown Chart


Previous Page Next Page  

It displays the total work remaining to achieve the sprint goal for a given time to sprint. It helps the team to manage the progress and respond accordingly. This chart is an important feature of Agile – Scrum methodology.

Generate a Report

To generate a report, the user should follow the steps given below.

Step 1 − Go to Project → choose a Specific project. Cpck on the Report icon on the left side of the menu. Go to Agile and cpck on Burndown chart. The following screenshot shows how to access a Burndown Chart.

Burndown Chart

Step 2 − It displays the Burndown chart of the sprint pke how the team is progressing towards a committed task. The red pne displays how much work is remaining, while the grey pne shows the committed tasks. The team can see where they stand in terms of the progress of sprint as compared to the commitment at the starting of that sprint. The user can change the Sprint and Y-axis by selection from a dropdown.

The following screenshot shows how the Burndown chart looks pke sprint wise.

Sprint Wise

Step 3 − In the second part of the report, it displays data pke what is the sprint start date, what all issues were added, day by day how many issues resolved, what story points of the issues are, and day-by-day how many story points are remaining. This data is utipzed to create the chart. The following screenshot shows the data that is used to generate the chart.

Generate Chart

Note − Quite similar to these reports, other reports can also be generated.

Advertisements