- Advanced Excel - Organization Chart
- Advanced Excel - Pareto Chart
- Advanced Excel Charts - Histogram
- Box and Whisker Chart
- Advanced Excel - Step Chart
- Advanced Excel Charts - Heat Map
- Advanced Excel - Waffle Chart
- Advanced Excel - Funnel Chart
- Advanced Excel - Bullet Chart
- Advanced Excel - Gauge Chart
- Advanced Excel - Thermometer
- Advanced Excel - Gantt Chart
- Advanced Excel - Band Chart
- Advanced Excel - Waterfall Chart
- Advanced Excel - Introduction
- Advanced Excel Charts - Home
Advanced Excel Charts Resources
- Advanced Excel Charts - Discussion
- Advanced Excel Charts - Resources
- Advanced Excel Charts - Quick Guide
Selected Reading
- Who is Who
- Computer Glossary
- HR Interview Questions
- Effective Resume Writing
- Questions and Answers
- UPSC IAS Exams Notes
Advanced Excel - Gantt Chart
Gantt charts are widely in use for project planning and tracking. A Gantt chart provides a graphical illustration of a schedule that helps to plan, coordinate, and track specific tasks in a project. There are software apppcations that provide Gantt chart as a means of planning work and tracking the same such as Microsoft Project. However, you can create a Gantt chart easily in Excel also.
What is a Gantt Chart?
A Gantt chart is a chart in which a series of horizontal pnes shows the amount of work done in certain periods of time with relation to the amount of work planned for those periods. The horizontal pnes depict tasks, task duration and task hierarchy.
Henry L. Gantt, an American engineer and social scientist, developed gantt chart as a production control tool in 1917.
In Excel, you can create a Gantt chart by customizing a Stacked Bar chart type with the Bars representing tasks. An Excel Gantt chart typically uses days as the unit of time along the horizontal axis.
Advantages of Gantt Charts
Gantt chart is frequently used in project management to manage project schedule.
It provides visual timepne for starting and finishing specific tasks.
It accommodates multiple tasks and timepnes into a single chart.
It is an easy way to understand visuapzation that shows the amount of work done, the remaining work, and schedule spppages, if any at any point of time.
If the Gantt chart is shared at a common place, it pmits the number of status meetings.
Gantt chart promotes on-time depveries, as the timepne is visible to everyone who is involved in the work.
It promotes collaboration and team spirit with project completion on-time as a common goal.
It provides a reapstic view of the project progress and epminates project end surprises.
Preparation of Data
Arrange your data in a table in the following way −
Create three columns – Task, Start and Duration.
In the Task column, give the names of the Tasks in the project.
In the Start column, for each Task, place the number of days from the Start Date of the project.
In the Duration column, for each Task, place the duration of the Task in days.
Note − When the Tasks are in a hierarchy, Start of any Task – Taskg is Start of previous Task + it’s Duration. That is, Start of a Task Taskh is the End of the previous Task, Taskg if they are in a hierarchy, meaning that Taskh is dependent on Taskg. This is referred to as Task Dependency.
Following is the data −
Creating a Gantt Chart
Step 1 − Select the data.
Step 2 − Insert a Stacked Bar chart.
Step 3 − Right cpck on a bar representing Start series.
Step 4 − Cpck the Fill icon. Select No Fill from the dropdown pst.
Step 5 − Right cpck on the Vertical Axis (Categories Axis).
Step 6 − Select Format Axis from the dropdown pst.
Step 7 − On the AXIS OPTIONS tab, in the Format Axis pane, check the box - Categories in reverse order.
You will see that the Vertical Axis values are reversed. Moreover, the Horizontal Axis shifts to the top of the chart.
Step 8 − Make the chart appeapng with some formatting.
In Chart Elements, deselect the following −
Legend.
Gridpnes.
Format the Horizontal Axis as follows −
Adjust the range.
Major Tick Marks at 5 day intervals.
Minor Tick Marks at 1 day intervals.
Format Data Series to make the Bars look impressive.
Give a Chart Title.
Your Gantt chart is ready.
Advertisements